Building project updates w/c 30 May

w/c 30 May

There are no works planned on site over the bank holiday weekend 28-30 May.

  • FF stripping and removing metal book shelves and racking
  • FF BLL light drilling and fixing for wooden shelves erection
  • GF WCs light noise works for electrics e.g.  pulling cables along conduit
  • GF old rare book store stripping and removing metal book shelves and racking
  • SF / FF / GF general cleaning and moving materials

Temporary ladies toilets have been installed outside of the building. Male toilets are available on the first floor, adjacent to the porters lodge.