Building project notices w/c 24th August 2015
Pre-Commencement Works:
- Internal hoarding work will commence on 24 August. This will take place from 6pm to 6am to minimise disruption.
- Isolations and disconnections will take place from 24 August. Any shut downs of areas will take place early i.e. 5am or late evening 9-10pm.
- Site compound in the Manor Road carpark will be fully operational from 25 August.