Building Notices w/c 21st September
Weekly update for w/c 21st September
Continued demolition to the Ground Floor areas
Soft strip progressively working up the building
Breaking out of the lift pit
Groundworks and drainage
From Monday through to Wednesday next week (21st – 23rd September) more noisy work will take place due to the use of machinery to take down the stairs and removing tougher elements of the masonry structure. Beard are aiming to be complete with these noisy works by Thursday the 24th September.