Building project notices w/c 30 November 2015
W/c 30 November 2015
7.30am – 9am Heavy demolition works in both BLL area and GF west toilet area.
9am – 4pm Light clearing of rubble
7.30am – 4.30pm Acoustic partitions being installed on the 1st and 2nd floor BLL area.
W/c 7 December 2015
Recommencement of groundwork including:
Chasing of floor for electrical containment (GF / 1st and 2nd)
Excavation of the BLL and main lift pit
Electrical & mechanical containment
Drainage – BLL area