Building project notices w/c 7 December 2015
W/c 7 December
Ground Floor West Main lift excavation and construction
Ground Floor West Demolition of dumbwaiter (65% complete)
Bodleian Law Library area Ground Floor BLL lift excavation and construction
Bodleian Law Library area Ground Floor Floor chasing (concrete cutting) and electrical containment
Bodleian Law Library area Ground Floor Drainage (2 locations)
Bodleian Law Library area Ground Floor Relocation of pipe work services
Bodleian Law Library area Ground Floor Electrical containment
Bodleian Law Library 1st floor Floor chasing (concrete cutting)
Bodleian Law Library 3rd Floor Acoustic panelling
Work will take place from 7:30am-5pm, Monday-Friday.
W/c 14 December
Mainly continuation of the above activities, they have a 2-3 week duration.
Additional activities include:
Bodleian Law Library area 2nd floor Floor chasing (concrete cutting)
Work will take place from 7:30am-5pm, Monday-Friday.
In case of any issues with noise levels, please contact Katie Light (katie.light@law.ox.ac.uk, 01865 618076) or Mike Thrift (mike.thrift@admin.ox.ac.uk, 01865 278761) in the first instance. Please do not enter the site area yourself as this is a Health and Safety risk.