W/c 7 December  

Ground Floor West                                                 Main lift excavation and construction

Ground Floor West                                                 Demolition of dumbwaiter (65% complete)

Bodleian Law Library area Ground Floor                 BLL lift excavation and construction

Bodleian Law Library area Ground Floor                 Floor chasing (concrete cutting) and electrical containment

Bodleian Law Library area Ground Floor                 Drainage (2 locations)

Bodleian Law Library area Ground Floor                 Relocation of pipe work services

Bodleian Law Library area Ground Floor                 Electrical containment

Bodleian Law Library 1st floor                                 Floor chasing (concrete cutting)

Bodleian Law Library 3rd Floor                                Acoustic panelling

Work will take place from 7:30am-5pm, Monday-Friday.

W/c 14 December

Mainly continuation of the above activities, they have a 2-3 week duration.

Additional activities include:

Bodleian Law Library area 2nd floor                           Floor chasing (concrete cutting)

Work will take place from 7:30am-5pm, Monday-Friday.

In case of any issues with noise levels, please contact Katie Light (katie.light@law.ox.ac.uk, 01865 618076) or Mike Thrift (mike.thrift@admin.ox.ac.uk, 01865 278761) in the first instance. Please do not enter the site area yourself as this is a Health and Safety risk.