Building project notices w/c 18 January 2016

w/c 18th January 2016

  • GF old IECL area cutting slab for drainage
  • FF stud partitions – drilling into concrete beams and floors
  • SF stud partitions – drilling into concrete beams and floors
  • SF wiring for electrics
  • SF fitting of electrical containment
  • GF BLL area formwork/reinforcement to stair infill
  • GF concrete pour to main lift pit base
  • GF concrete pour to BLL lift pit base
  • External – bricklaying to delivery bay extension
  • GF BLL lift pit laying waterproofing
  • GF BLL area fixing and drilling for metal frame ceiling
  • SF BLL area fixing and drilling for metal frame ceiling


Works expected to be completed during the following week (w/c 25th Jan) are as follows:

  • GF WCs internal bricklaying
  • GF WCs stud partitions – drilling into concrete beams and floors
  • FF BLL area fixing and drilling for metal frame ceiling
  • SF BLL area fixing and drilling for metal frame ceiling
  • External – bricklaying to delivery bay extension