Building project notices w/c 18 January 2016
w/c 18th January 2016
- GF old IECL area cutting slab for drainage
- FF stud partitions – drilling into concrete beams and floors
- SF stud partitions – drilling into concrete beams and floors
- SF wiring for electrics
- SF fitting of electrical containment
- GF BLL area formwork/reinforcement to stair infill
- GF concrete pour to main lift pit base
- GF concrete pour to BLL lift pit base
- External – bricklaying to delivery bay extension
- GF BLL lift pit laying waterproofing
- GF BLL area fixing and drilling for metal frame ceiling
- SF BLL area fixing and drilling for metal frame ceiling
Works expected to be completed during the following week (w/c 25th Jan) are as follows:
- GF WCs internal bricklaying
- GF WCs stud partitions – drilling into concrete beams and floors
- FF BLL area fixing and drilling for metal frame ceiling
- SF BLL area fixing and drilling for metal frame ceiling
- External – bricklaying to delivery bay extension