Building project notices w/c 25 January 2016
Ways to progress works in the GF toilet area are being considered. An update will follow once working times have been confirmed.
Works on Saturday 23rd January
- GF BLL area - Plasterboard walls and ceilings
w/c 25th January
- GF bricklaying to BLL and main lift and internal walls
- GF/FF/SF BLL area drilling and fixing into concrete for mechanical/electrical works
- GF/FF/SF BLL area fixing and drilling into concrete for metal frame ceiling
- GF BLL area plaster skim to partitions and ceilings
- GF BLL lift shaft waterproof laying
- SF BLL area screwing plasterboard to metal frame grid
- BLL lift shaft drilling and screwing into timber for formwork
- External – bricklaying to BLL book delivery extension
- External – scaffold erection for BLL book delivery extension
Works that are expected to be completed during the week after (w/c 1st Feb) are as follows:
- FF/SF BLL area screwing plasterboard to metal frame ceiling
- FF/SF BLL area plaster skim to partitions and ceilings
- GF BLL area decorations/painting to walls and ceilings
- GF BLL lift ground bearing slab reinstatement
- External – fixing timber joists for roof structure of book delivery extension