Building project notices w/c 1 February 2016
w/c 1 February
- SF BLL area fixing and drilling into metal frame for plasterboard ceiling
- SF BLL area fixing and drilling into concrete for mechanical/electrical works
- FF BLL area fixing and drilling into metal frame for plasterboard ceiling
- FF electricians pulling cables from BLL to existing building
- GF BLL area fixing and drilling into concrete for metal frame ceiling
- External – bricklaying to book delivery extension
- SF plastering to walls
- FF plastering to walls
- GF BLL lift shaft taking out formwork and laying waterproofing
- GF BLL lift shaft reinstating ground bearing slab
- GF main lift (below toilets) breaking out concrete for drain runs (1pm-5pm) – Tuesday only
Works that are expected to take place during the following week (w/c 8 Feb) are:
- SF / FF BLL area plastering to walls and ceilings
- SF BLL area mist coat to walls
- SF / FF fixing and drilling into concrete for mechanical/electrical works
- GF BLL area fixing and drilling into metal frame for plasterboard ceiling
- BLL lift shaft block laying for walls
- External – bricklaying to book delivery extension