Building project notices w/c 1 February 2016

w/c 1 February

  • SF BLL area fixing and drilling into metal frame for plasterboard ceiling
  • SF BLL area fixing and drilling into concrete for mechanical/electrical works
  • FF BLL area fixing and drilling into metal frame for plasterboard ceiling
  • FF electricians pulling cables from BLL to existing building
  • GF BLL area fixing and drilling into concrete for metal frame ceiling
  • External – bricklaying to book delivery extension
  • SF plastering to walls
  • FF plastering to walls
  • GF BLL  lift shaft taking out formwork and laying waterproofing
  • GF BLL lift shaft reinstating ground bearing slab
  • GF main lift (below toilets) breaking out concrete for drain runs (1pm-5pm) – Tuesday only

Works that are expected to take place during the following week (w/c 8 Feb) are:

  • SF / FF BLL area plastering to walls and ceilings
  • SF BLL area mist coat to walls
  • SF / FF fixing and drilling into concrete for mechanical/electrical works
  • GF BLL area fixing and drilling into metal frame for plasterboard ceiling
  • BLL lift shaft block laying for walls
  • External – bricklaying to book delivery extension