Building project notices w/c 15 February

w/c 15th February

  • SF / FF / GF BLL drilling and fixing into concrete for mechanical and electrical works
  • GF mist coat to walls and ceilings
  • GF BLL drilling into concrete floor for metal plates and roller bases for racking
  • GF BLL fixing and drilling into concrete for metal frame ceiling
  • GF BLL plaster skim to walls
  • External – bricklaying for book delivery extension
  • GF WC breaking out of concrete for drainage – Tuesday, Wednesday, Friday between 1-5pm.
  • GF BLL fixing and drilling into metal for plasterboard ceiling
  • SF breaking out of concrete floor for BLL lift shaft (Wednesday and Thursday only)

 

Please also find below a list of activities which are expected to take place during w/c 22nd February.

  • SF / FF / GF BLL drilling and fixing into concrete for mechanical and electrical works
  • SF / FF / GF mist coat to walls and ceilings
  • GF BLL fixing shelving for racking
  • External – bricklaying for book delivery extension
  • Noisy works in GF WCs limited to 1-5pm on Tuesday and Friday only