Building project notices w/c 22 February

w/c 22 February

  • SF / FF / GF BLL drilling and fixing into concrete for mechanical and electrical works
  • SF / GF paint to walls
  • GF BLL drilling into concrete floor for metal plates and roller bases for racking
  • GF BLL fixing and drilling into metal for plasterboard ceiling
  • GF plaster skim to walls and ceilings
  • External – bricklaying to book delivery extension
  • GF WCs breaking out of concrete for drainage. Tuesday and Friday between 1-5pm.
  • SF / FF / GF BLL drilling and fixing into concrete for mechanical and electrical works – in between 7.30am-10am and 12pm-2pm on Wednesday 24th.
  • SF latex for floor finishes
  • GF BLL drilling into concrete floor for metal plates and roller bases for racking – in between 7.30am-10am and 12pm-2pm on Wednesday 24th.
  • External – scaffold erection for book delivery extension roof structure
  • External – fixing timber joists for book delivery extension roof structure

 Expected activities to take place during w/c 29 February

  • GF WCs breaking out concrete for drainage. Tuesday, Wednesday and Friday between 1-5pm
  • SF / FF / GF latex for floor finishes
  • SF / FF / GF BLL drilling and fixing into concrete for mechanical and electrical works
  • GF BLL drilling into concrete floor for metal plates and roller bases for racking
  • External – fixing timber joists for book delivery extension roof structure