Building project notices w/c 22 February
w/c 22 February
- SF / FF / GF BLL drilling and fixing into concrete for mechanical and electrical works
- SF / GF paint to walls
- GF BLL drilling into concrete floor for metal plates and roller bases for racking
- GF BLL fixing and drilling into metal for plasterboard ceiling
- GF plaster skim to walls and ceilings
- External – bricklaying to book delivery extension
- GF WCs breaking out of concrete for drainage. Tuesday and Friday between 1-5pm.
- SF / FF / GF BLL drilling and fixing into concrete for mechanical and electrical works – in between 7.30am-10am and 12pm-2pm on Wednesday 24th.
- SF latex for floor finishes
- GF BLL drilling into concrete floor for metal plates and roller bases for racking – in between 7.30am-10am and 12pm-2pm on Wednesday 24th.
- External – scaffold erection for book delivery extension roof structure
- External – fixing timber joists for book delivery extension roof structure
Expected activities to take place during w/c 29 February
- GF WCs breaking out concrete for drainage. Tuesday, Wednesday and Friday between 1-5pm
- SF / FF / GF latex for floor finishes
- SF / FF / GF BLL drilling and fixing into concrete for mechanical and electrical works
- GF BLL drilling into concrete floor for metal plates and roller bases for racking
- External – fixing timber joists for book delivery extension roof structure