Building Project Notices w/c 29 February

There will be quiet working from 10-12 on Wednesday 2nd and Thursday 3rd March due to some lectures which could not be rescheduled to the Examination Schools.

Please note that setting out works have been taking place in the ladies toilets on the first floor and in the JCR on the 2nd floor. These works will continue on the 25th of February and one day next week (to be confirmed). These areas will remain open during these works.

w/c 29th February:

  • GF BLL fixing shelving for mobile racking
  • TF breaking out roof slab for BLL lift shaft
  • SF / FF / GF paint to walls
  • SF / FF / GF latex for floor finishes
  • SF / FF / GF drilling and fixing into concrete for mechanical and electrical works
  • External – bricklaying for book delivery extension
  • GF WCs breaking out concrete for drainage – Tuesday/Wednesday 1-5pm, Friday 2-5pm
  • TF reading rooms redirecting rainwater pipes
  • External – fixing timber joists for book delivery extension roof structure

Please also find below a list of activities which are expected to take place in the week w/c 7th March:

  • GF WCs breaking out concrete for drainage – Tuesday/Wednesday/Friday 1-5pm
  • GF BLL fixing shelving for mobile racking
  • SF / FF / GF laying of floor finishes
  • SF / FF / GF paint to walls
  • External – fixing timber joists for book delivery extension roof structure