Building project notices w/c 7 March
There will be quiet working from 10-12 on Tuesday 8th and Wednesday 9th March due to some lectures which could not be rescheduled to the Examination Schools. This is in addition to the quiet working slots from 11-12 each day.
w/c 7th March
- SF / FF / GF drilling and fixing into concrete and metal for mechanical and electrical works
- SF / FF / GF paint to walls
- GF BLL drilling and fixing into concrete for metal frame ceiling
- GF BLL fixing shelving for mobile racking
- GF BLL latex for floor finishes
- External – fixing timber joists for book delivery extension roof structure
- TF demolition of lift shaft walls
- GF BLL drilling and fixing for stud partition installation
- SF plaster skim to walls
- BLL stack staircases demolition using Brock machine
- TF bricklaying for new lift shaft walls
Expected activities during the w/c 14th March
- SF / FF / GF drilling and fixing into concrete and metal for mechanical and electrical works
- External – fixing timber joists for book delivery extension roof structure
- GF BLL fixing shelving for mobile racking
- TF bricklaying for new lift shaft walls
Please note that a power shutdown to part of the building is planned on Sunday the 20th March.