Please note: Phase B works are scheduled to commence next week. This will include works to the toilets on the first floor and to the JCR/ SCR area on the second floor and these areas will be closed from Monday 14th March.

Arrangements have been made for the relocation of the Missing Bean for Trinity Term and information about this will be circulated in due course. By kind permission of the English Faculty, students and staff are able to use the English Graduate Common Room on the first floor whilst the JCR and SCR are inaccessible. Users of this space should take note of the bookings in the common room which will be displayed on the door, when the common room is booked for another event it will be closed to other users.

Please note that amended working hours on the 14th, 15th, 16th March are due to the Law Open Days taking place.

w/c 14th March

  • GF paint to walls
  • SF / FF / GF drilling and fixing into concrete and metal for mechanical and electrical works. Monday, Tuesday and Wednesday 1-5pm, and all day Thursday and Friday.
  • SF laying of floor finishes
  • SF drilling and fixing into metal for plasterboard partitions
  • GF WCs fixing of shuttering and reinforcement for formation of main lift pit
  • External – fixing timber joists for book delivery extension roof structure
  • External – cutting back 3rd floor slab for BLL lift shaft
  • GF drilling for and fixing of door frames
  • GF drilling and fixing into metal frame for plasterboard ceiling

Activities expected to take place in the following week (w/c 21st March)

  • GF WCs fixing of shuttering and reinforcement for formation of main lift pit
  • External – fixing timber joists for book delivery extension roof structure
  • External – TF bricklaying for BLL lift shaft
  • SF / FF / GF drilling and fixing into concrete and metal for mechanical and electrical works
  • FF / GF laying of floor finishes

Please note that a power shutdown to part of the building is planned on Sunday the 20th March.