Building project notices w/c 28 March

Week commencing 28th March:

  • GF WC breaking through concrete for drainage works
  • GF WC drilling and fixing into concrete and metal for stud partitions
  • SF / GF laying of floor finishes
  • GF book delivery extension plaster skim to walls
  • Phase B SF / FF main core heavy demolition works
  • Phase B North Wing heavy demolition works
  • Phase B GF Criminology North breaking through concrete for drainage works
  • Phase B SF / FF drilling and fixing into concrete for timber infills
  • GF WC drilling and fixing into concrete and metal for metal frame ceiling
  • GF book delivery extension paint to walls
  • TF lift shaft steel trimming for lifting eye

Please also find below a list of activities expected to take place during the following week (w/c 4 April)

  • Phase B SF / FF main core heavy demolition works
  • Phase B North Wing drilling and fixing into concrete for timber infills
  • Phase B GF Criminology North breaking through concrete for drainage works
  • Phase B SF / FF drilling and fixing into concrete for timber infills
  • Phase A installation of 2nd fix items – light switches, sockets, sinks etc.