Building project notices w/c 4 April

w/c 4 April:

  • GF WCs breaking out of concrete for drainage works
  • GF book delivery extension fixing lights switches, sockets, ironmongery etc.
  • TF BLL lift shaft drilling and fixing timber to roof structure
  • SF / FF Main Core heavy demolition works
  • SF / FF / North Wing drilling and fixing into concrete for timber infills
  • GF Criminology North breaking through concrete for drainage works

Activities expected to take place during the following week (w/c 11 April):

  • GF WCs reinstating ground bearing slab
  • GF book delivery extension laying floor finishes
  • GF book delivery extension paint to walls
  • TF BLL lift shaft fixing roof coverings
  • SF / FF Main Core heavy demolition works
  • SF / FF / North Wing heavy demolition works
  • GF Criminology North heavy demolition works