w/c 11 April:

  • GF WCs breaking out of concrete and reinstating concrete for drainage works
  • GF WCs bricklaying for internal walls
  • GF book delivery extension plaster to walls and ceilings
  • GF book delivery extension drilling and fixing for metal stud partitions and ceilings
  • SF / FF Main Core heavy demolition works
  • SF / FF North Wing heavy demolition works
  • FF Main Core area drilling and fixing of permanent steel work – with crane lift on Wednesday

Activities expected to take place w/c 18 April:

  • GF WCs reinstating concrete for drainage works
  • GF WCs drilling and fixing into concrete for metal frame ceiling, partitions, mechanical and electrical works
  • GF WCs drilling and fixing into metal for plasterboard ceiling and partitions
  • Phase A SF / FF / GF final snags and finishes
  • FF Main Core drilling and fixing of permanent steel work
  • SF / FF Main Core tidying and cleaning ready for Trinity Term.