Building project notices w/c 11 April
w/c 11 April:
- GF WCs breaking out of concrete and reinstating concrete for drainage works
- GF WCs bricklaying for internal walls
- GF book delivery extension plaster to walls and ceilings
- GF book delivery extension drilling and fixing for metal stud partitions and ceilings
- SF / FF Main Core heavy demolition works
- SF / FF North Wing heavy demolition works
- FF Main Core area drilling and fixing of permanent steel work – with crane lift on Wednesday
Activities expected to take place w/c 18 April:
- GF WCs reinstating concrete for drainage works
- GF WCs drilling and fixing into concrete for metal frame ceiling, partitions, mechanical and electrical works
- GF WCs drilling and fixing into metal for plasterboard ceiling and partitions
- Phase A SF / FF / GF final snags and finishes
- FF Main Core drilling and fixing of permanent steel work
- SF / FF Main Core tidying and cleaning ready for Trinity Term.