Please note: As advised separately, a crane will be on site to lift steels to the 2nd floor on Monday 18 April. The crane will be situated on the standing at the front of the building. Banksmen will be in place to ensure safety at all times. On Monday please use the Manor Road doors to enter and exit the building as the main stairs will not be accessible for Health and Safety Reasons.

A porter will be in place at the Manor Road entrance to open the doors for those without swipe access and to direct users around the building.

Works w/c 18 April

  • GF WCs reinstating concrete for drainage works
  • GF WCs drilling and fixing into concrete for metal frame ceiling, partitions, mechanical and electrical works
  • GF WCs drilling and fixing into metal for plasterboard ceiling and partitions
  • Phase A SF / FF / GF final snags and finish – occasional drilling and fixing may be required
  • GF – FF stack stair removal areas drilling and fixing for partitions and ceilings
  • FF Main Core drilling and fixing of permanent steel – with crane lift
  • SF / FF / GF Main Core tidying and cleaning ready for Trinity term
  • GF – FF stack stair removal areas drilling and fixing for partitions and ceilings
  • BLL lift shaft stripping and removing scaffold

Works w/c 25 April

Acoustic tests will take place during w/c 18 April to determine the activities which may take place during this week. Further information will be circulated in due course.