There are works planned on site for Saturday morning (2nd July) - this will consist of medium to low noisy works. There are no works planned on site on Sunday 3rd July.

w/c 4th July

  • Main Core, English Faculty, BLL & Criminology (GF/FF/SF) - drilling & fixing for hoarding erection
  • Main Core, English Faculty & Criminology (GF / FF / SF / TF) Heavy demolition works throughout
  • Main Core Toilets (GF) - drilling & fixing into concrete & metal for partitions
  • Main Core, English Faculty & Criminology (GF / FF / SF) - stripping and light demolition works
  • Main Core Toilets (GF) - drilling & fixing into concrete & metal for partitions
  • Main Core (FF/SF) - bricklaying for internal walls
  • Main Core, English Faculty, BLL & Criminology (GF/FF/SF) - Mechanical & Electrical disconnections
  • BLL Lift (GF / FF / SF) - installation of lift
  • Main Core, English Faculty, BLL & Criminology (GF/FF/SF) - drilling & fixing for partitions
  • DDA Entrance area (GF) stripping electrical fittings and lights and mechanical pipes
  • DDA Entrance area (GF) light demolition works and dismantling/stripping furniture and timber
  • DDA Entrance area (GF) heavy demolition for window/ walls
  • Main Core, English Faculty & Criminology (GF/FF/SF/TF) Heavy breaking out of concrete

Please note that the temporary toilet facilities are being collected during w/c 4th July. Toilet facilities are available on the GF next to the Cube, and on the First Floor adjacent to the English Graduate Common Room.

Bike racks at the back of the building (near the Manor Road entrance) under the building overhang have been reopened.

The readers' entrance to the Law Library has moved to a ground floor door, off the lane which runs between the St Cross Building and the Manor Road Building.

During the summer the main entrance to the building will be undergoing refurbishment, and the porters will be relocating from their current space to a desk in the foyer.