Building project updates w/c 18 July
There are medium to high level noisy works planned on site for this coming Saturday morning (7.30am-1pm) - 16th July.
w/c 18th July
Main Core, English Faculty, BLL & Criminology (GF/FF/SF) - drilling & fixing for hoarding erection
Main Core and English Faculty (GF / FF / SF / TF) Heavy demolition works throughout
Main Core Toilets (GF) - drilling & fixing into concrete & metal for partitions
Main Core, English Faculty, BLL & Criminology (GF/FF/SF) - fixing & drilling for mechanical & electrical works
BLL Lift (GF / FF / SF) - installation of lift
Main Core, English Faculty, BLL & Criminology (GF/FF/SF) - drilling & fixing for partitions
DDA Entrance area (GF) heavy demolition works
DDA Entrance area (GF) drilling and fixing for electrical works
MONDAY Crane lifting steel on main entrance external stairs
Toilet facilities are available on the GF next to the Cube, and on the First Floor adjacent to the English Graduate Common Room.
Bike racks at the back of the building (near the Manor Road entrance) under the building overhang have been reopened.
The readers' entrance to the Law Library has moved to a ground floor door, off the lane which runs between the St Cross Building and the Manor Road Building.
The porters have relocated to a desk by the Manor Road entrance to the building.