Building project updates w/c 5 September
There are some medium to high level noisy works planned on site on Saturday 10th September from 8am-1pm.
w/c 5th September
- BLL North area (GF) painting and finishing to walls
- Main Core Toilets (GF) - drilling & fixing into concrete & metal for partitions
- Criminology (FF) - drilling and fixing for glazed screen partitions installation
- Criminology (FF) - paint to walls
- Main Core, English Faculty, BLL & Criminology (GF/FF/SF) - fixing & drilling for mechanical & electrical works
- Main Core, English Faculty, BLL & Criminology (GF/FF/SF) - plastering to walls and ceilings
- Main Core, English Faculty, BLL & Criminology (GF/FF/SF) - drilling & fixing for ceiling and partitions
- DDA Entrance area (GF) drilling and fixing for ceiling and partitions erection
- BLL North area (GF) fixing and drilling for electrical fittings
- DDA Entrance (GF) plaster skim to walls and ceilings
- External works - excavating out for external path on west elevation
- DDA Entrance (GF) drilling and fixing for internal door installation
Toilet facilities are available on the GF next to the Cube, and on the First Floor adjacent to the English Graduate Common Room.
Bike racks at the back of the building (near the Manor Road entrance) under the building overhang have been reopened.
The porters have relocated to a desk by the Manor Road entrance to the building.