Building project updates w/c 26 September

*Please note that there will be a data shutdown on Tuesday 27th September between 7:30 – 9am to enable work on fibre cables* There will be no internet or VOIP phones during this time.

w/c 26th September

  • FF Toilets - Paint to walls and ceilings
  • FF Criminology - making good to walls and ceilings
  • FF Main Core - drilling and fixing for ceilings and partitions installation
  • SF Main Core - drilling and fixing for ceilings and partitions installation
  • SF Café area - drilling and fixing for ceilings and partitions installation
  • SF Toilets - drilling and fixing for cubicles and mechanical fit out
  • TF IECL area - drilling and fixing for ceilings and partitions installation
  • TF IECL area - drilling and fixing for 2nd fix mechanical and electrical
  • FF Toilets - latex to floors
  • FF Toilets - floor laying

Toilet facilities are available on the GF next to the Lecture Theatre 2 and next to the Cube, and on the First Floor adjacent to the English Graduate Common Room.

Bike racks at the back of the building (near the Manor Road entrance) under the building overhang have been reopened.