Building project updates w/c 3 October

No noisy works will take place on Tuesday 4th October (pm) and Friday 7th October (pm).

w/c 3rd October

  • FF Toilets - latex to floors
  • FF Criminology - making good to walls and ceilings
  • FF Baker Mckenzie - painting and making good to walls and ceilings
  • FF Main Core - drilling and fixing for ceilings and partitions installation
  • SF Main Core - drilling and fixing for ceilings and partitions installation
  • SF Café area - latex to floors
  • SF Toilets - drilling and fixing for cubicles and mechanical fit out
  • TF IECL area - drilling and fixing for ceilings and partitions installation
  • TF IECL area - drilling and fixing for 2nd fix mechanical and electrical
  • FF Toilets - floor laying
  • FF Baker Mckenzie - drilling and fixing for electrical 2nd fix items
  • SF Café area - floor laying
  • FF Baker Mckenzie - floor laying
  • SF Café area - drilling and fixing for mechanical and electrical 2nd fix
  • FF Toilets - builders clean
  • FF Baker Mckenzie - Builders clean

Toilet facilities are available on the GF next to the Lecture Theatre 2 and next to the Cube, and on the First Floor adjacent to the English Graduate Common Room.

Bike racks at the back of the building (near the Manor Road entrance) under the building overhang have been reopened.

The English Faculty Library will reopen to readers on Tuesday 4th October.

The BLL main entrance will open on Wednesday 5th October.