Building project updates w/c 7 November
There are medium to high level noisy works planned on site for this coming Saturday morning (8am-1pm) - 12th November.
w/c 7th November
- FF Criminology - final finishes, painting and decorating
- SF Main Core / Stairs - drilling and fixing for mechanical and electrical fixings and glazed screen installations
- SF Toilets - drilling and fixing for 2nd fix mechanical and electrical fixings and tiling to walls and floor laying
- TF Main Core - drilling and fixing for electrical fixings and glazed screen installations, and floor laying
- Main Lift Shaft - drilling and fixing/moving materials for main lift installation
New toilets have now opened on the first floor near to the main building reception and on the Ground Floor next to Lecture Theatre 2.
Bike racks at the back of the building (near the Manor Road entrance) under the building overhang have been reopened.