Building project update w/c 21 November
There are medium to high level noisy works planned on site for this coming Saturday morning (8am-1pm) - 19th November.
w/c 21st November
- FF Criminology - final finishes, painting, decorating and cleaning
- FF Rear entrance stairs - painting and decorating
- SF Main Core / Stairs - floor laying and painting and decorating
- SF Toilets - painting and decorating
- TF Main Core - drilling and fixing for electrical fixings and glazed screen installations, and floor laying
- Main Roof - fixing and drilling for roof installation
- Main Lift Shaft - drilling and fixing/moving materials for main lift installation
New toilets have now opened on the first floor near to the main building reception and on the Ground Floor next to Lecture Theatre 2.
Bike racks at the back of the building (near the Manor Road entrance) under the building overhang have been reopened.