Building project updates 6 January
6th January
Floor polishing in the new main core stairs taking place, 2nd floor Law offices and 3rd floor IECL to be accessed using new lift during this time
w/c 9th January
- Canopy Scaffold being taken down on Tuesday 10th January
- Cork remedial works to BLL from Monday for a 1 week period
- 2-3 men on snagging for 1 week
- Bike hoops and loud jack hammer works until Thursday 12th January
w/c 16th January
- Provisional date for all scaffolding removal Tuesday 17th January
- Containers / Heras fencing removal and final remedial works provisionally scheduled to be complete by 20th January